Designs That Work
Very
Cold Climate: Aspen Profile
PDF Version
Cross Section

Construction Recommendations
- Foundation: Conditioned crawlspace
- Above Grade Walls: Wood frame
- Cladding: Fiber cement battened panels
- Attic: Cathedral living space
- Roof: Standing seam metal
Building Science Notes
- Ducts in conditioned space - This building profile is
designed to accommodate HVAC equipment and ducts in the crawlspace and
second-story eaves behind knee walls. HVAC ducts should not be run in
exterior walls.
- Conditioned crawlspace - Conditioning of the crawlspace means
that this space must be constructed much like a living space - it must
be supplied by the HVAC system and have a transfer grille to return air
back to the HVAC system located in the living space. The supply air
should be directed horizontally across the crawlspace with good enough
"throw" to provide some mixing, not directed down at the floor. Sizing
of the supply air should be about 5% of the conditioned crawlspace floor
area (For example: 0.05 cfm/ft2*1600ft2=80 cfm for
a 1,600 ft2 conditioned crawlspace). A single 6-inch diameter
supply duct typically suffices. Transfer air should go back to the
central area of the living space above the crawlspace. Two grilles (10
inches by 4 inches) on opposite sides of the crawlspace will usually be
sufficient. The transfer area should be calculated in the same manner as
for closed bedrooms connecting to hallways, using the 3 Pa pressure
difference limit. Some form of mechanical moisture control for the
crawlspace is necessary. We recommend one of the following approaches:
- A controlled ventilation strategy using the intermittent central
fan-integrated supply - it provides both mixing and moisture removal
for the crawlspace as well as the house.
- A stand-alone dehumidifier installed in the crawlspace.
- A continuously-operating crawlspace exhaust fan with make-up air
extracted from the house.
In this assembly the rigid insulation is applied to the interior face
of the exterior foundation walls. The R-value of the rigid insulation
should follow the requirements for basement insulation in the most
recent International Energy Conservation Code (IECC). Moisture control
is important to proper performance; in particular, the vapor barrier
ground cover on the floor of the crawlspace must be continuous and
sealed to the perimeter wall and any supporting piers.

Figure 1 |
- Air sealing details at transitions - Air sealing can be
particularly difficult, but no less important, at assembly transitions
such as band joists, and between attached garages and living spaces.
These are discussed below because they have proven to be a consistent
challenge for builders.
-
Band joists - Continuity of an exterior air barrier can be
maintained at the band joist with sealed or taped housewrap or rigid
foam insulation. Continuity of an interior air barrier can be
maintained through a combination of cut foam blocks and sealant/caulk,
rigid draftstopping material (wood blocking) and sealant/caulk, or
spray foam. Note that neither cellulose nor fiberglass (batt or blown)
can be used for the air barrier. The air barrier detail on
second-story band joists is important because it is inaccessible
(covered by structural/finish floor and ceiling finish) after
construction. Note that while fiberglass batts fulfill the requirement
for protection from ignition in the open band joists, fiberglass batt
material by itself cannot maintain the air barrier.
-
Attached garages - the building enclosure surfaces shared between
conditioned space and an unconditioned garage must have a continuous air
barrier. See Figure 1 for details in terms of using sealants and
rigid insulation to create a continuous air barrier between the attached
garage and living space. See
Air Sealing / Air
Drywall Approach Details.
Climate Specific Details
-
Below-grade insulation - Ground temperatures make foundation wall
and slab insulation an important part of the thermal barrier.
-
Above-grade insulation - Homes in this climate benefit from
exterior insulation that warms whatever structural material is to its
interior, protecting it from the moisture degradation that can occur as
the result of condensation.
-
Ice dam protection - The combination of adequate insulation just
above the exterior wall, and air sealing at the wall-roof assemblies
transition are essential to prevent ice dams. But ice dams can occur even
in properly detailed roof assemblies from differential solar snow melt. A
water protection membrane over the entire roof surface is recommended on
all roof assemblies in this climate.
-
Mechanicals

Figure 4 |

Figure 5 |
- Humidification - In Very Cold climates, where some form of
winter-time humidification may be demanded by the occupants, a
humidistat must be installed so that occupants can monitor and keep the
relative humidity no higher than occupant comfort demands. For more
information see
Relative Humidity.
-
UV exposure - High altitude environments have significantly higher
UV exposures than lower altitude environments. This should be taken into
consideration in the selection of roof and wall claddings, as well as
windows (in terms of glazing properties). Masonry building materials
(roof tiles, brick, stucco) are naturally more UV-resistant. Many metal
wall and roof claddings are more UV-resistant - depending on the nature
and quality of finish - ask your product supplier for standardized test
information on the UV performance of all materials used on the exterior
of the building.

Figure 6
|

Figure 7 |
Field Experience Notes
-
Selection of rigid insulation - Most builders select rigid
insulation based on costs and handling properties, not material
properties such as vapor permeability. This and other Building Profiles
show XPS in most wall assemblies because it is generally preferred by
builders as "tougher" than EPS. This is often because the right type of
EPS is not being carried for building applications - see the
Building Materials Property Table for more information on both EPS
and XPS. But remember, the type of sheathing to use is always a question
that should be asked in the context of the given cladding, the level of
control that can be expected over interior relative humidity via
mechanical ventilation, and the amount and direction of drying potential
the wall assembly requires. See "Insulations,
Sheathings, and Vapor Diffusion Retarders" and Material
Compatibility and Substitutions for more information.
-
Joint treatment in rigid insulation - The type of rigid foam
insulation best suited for multifunctional application including the
drainage plane, shiplapped rigid foam insulation has proven to be
available in only very limited areas. Mastic works as a water sealant;
its long term performance is not known but appears promising. The
flexible flashing with polyethylene film is straightforward and creates
a natural weatherlap and therefore is the preferred approach.
-
Flashing details - Both the rough opening and the window should
be flashed - either one can leak. Note that installation of windows before
or after the drainage plane (in this case the rigid insulation) affects
the flashing sequence, how much of the flanged window extends outside
the plane of drainage, and window trim details.
-
Advanced framing - For a technical resource that
may help with resistance to advanced framing methods from local code
officials, see the
Building Safety Journal article written by
Peter
Yost of BSC.
-
Stepped foundation insulation detail -
Maintaining thermal barrier continuity in stepped foundations has proven
difficult or easy to neglect. Figure 6 shows how the rigid foam needs to
be cut and placed.
-
Eave insulation - the spray foam insulation stop between rafters
in the roof assembly can be either blocking (see Figure 7) or
rigid insulation from the wall cut out to extend up and between each
rafter.
-
Unvented roof assembly - There are other approaches to unvented
roof assemblies in very cold climates - the one portrayed in this assembly
is among the more cost-effective. See Material
Compatibility and Substitutions for more information.
Material Compatibility and Substitutions
-
Cavity insulation in the unvented roof assembly - There are
essentially four ways to manage heat, air, and moisture flow in an
unvented roof assembly in very cold climates:
NOTE: only the fourth option can involve cavity fill insulation
other than spray foam - spray foam is the only uniform, air-impermeable
cavity fill insulation appropriate for the first three options.
- Fill the entire framing cavity with low-density spray foam
insulation and install 1-inch rigid foam insulation to the interior of
the framing. In this case, the spray foam insulation effectively moves
the first condensing surface to the inside of the assembly, and the
rigid insulation both protects thermal bridging and condensation
potential at the rafters and lowers the permeability of the interior of
the system (open cell spray foam being about 10 perms and 1-inch of XPS
rigid foam insulation being about 1 perm). This system is best suited
for rafter framing and is the system shown in this building profile.
- Install spray foam insulation to the depth desired or required for
R-value and, after the foam has cured, cover the inside surface of the
spray foam with either latex paint or (if code considerations require a
system of protection against combustion) install gypsum board painted
with latex paint. This system moves the first condensing surface to the
inside face of the cavity insulation and is best suited for roof truss
framing because the spray foam depth encapsulates all roof framing
(except portions of the webs). See the "Boston"
building profile.
- Install high-density spray foam as the cavity insulation. Its vapor
permeability is low enough that no latex paint coating is required,
although gypsum wallboard or fiberglass insulation with foil facing may
be required for code compliance (See the
Boston Building Profile).
- Install enough rigid insulation to the exterior of the structural
system (roof sheathing and framing) to warm the structural system and
prevent condensation (the first condensing surface is the exterior
surface of the structural roof sheathing). The general rule of thumb is
1-4-inch of rigid foam per 1,000 heating degree days (but this rule
involves the interior conditions as well - interior relative humidity
during the coldest months affects the level of exterior rigid insulation
required to manage condensation). In very cold climates, this involves
deep enough rigid insulation to require another layer of sheathing on
the exterior of the insulation to act as the nailing base for the roof
cladding. This system works for any type of roof framing system but is
not very common because of relative first cost
-
Rigid Insulation - There is a significant difference in the vapor
permeability rigid insulations (see the
Building Materials Property Table). Along with thermal considerations,
consider the rigid insulation that best suits the wall assembly's need for
managing the flow of moisture into (wetting) and out of (drying) the
entire wall assembly.
-
Rim joist material - The dimensional stability (less shrinkage) of
engineered wood versus solid sawn make this a better choice for this deep
framing member. An alternative that also deals with the thermal
difficulties of this area of the assembly is a Structural Insulated Panel
(SIP) band joist. BSC Primary/Documents/HTW_Aspen 12 of 13
-
Rim joist blocking - An alternative to this detail is to spray foam
insulation on the rim joist to maintain air barrier continuity at this
transition.
-
Drainage plane on rigid insulation - An alternative to flashing, shiplapping, or sealing the XPS insulation for continuity of the drainage
plane is to apply a housewrap to the outside of the insulation; a
corrugated one such as StuccoWrap® also provides an air space (see the
Boston Building Profile). The housewrap
then becomes the continuous drainage plane.
-
Interior latex paint - The substitution of low permeability
interior finishes (vinyl wall paper, oil-based paints) for latex paint is
not recommended.
-
Cavity insulation materials - Acceptable cavity insulation includes
any that have a relatively high vapor permeability - cellulose, fiberglass,
foam (as long as air sealing is accomplished by a separate component or
system when cellulose or fiberglass is used). User discretion can be based
on properties other than building science.
-
Gypsum wallboard - Areas of potentially high moisture, such as
bathrooms, basements, kitchens, are excellent candidates for non-paper
faced wallboard systems (e.g. James Hardie's Hardibacker®, GP's DensArmor®,
USG's Fiberock®). In addition, paper-faced gypsum board should never be
used as interior sheathing or backer for tub or shower surrounds where
ceramic tile or marble (any material with joints or grout lines) is used
as the finish.
-
Cast concrete foundation walls - If block is used instead of cast
concrete for foundation walls, the bond beam becomes essential to maintain
air barrier continuity at the top of the block wall.
-
L-channel detail on cladding at base of exterior wall - Any stop
can be used at the bottom, exposed edge of the rigid insulation to prevent
insect and rodent intrusion, as long as it does not interfere with the foam's function as the drainage plane.
|